Il DURC di congruità (labour-cost adequacy certificate) checks whether the labour declared on a building project fits the value of the work.
What it is for
Congruità is a proportion. It compares the labour actually declared for a project with the labour that work of that value and that kind should normally have needed.
The idea behind it is simple. A building that cost a certain amount to put up cannot have been built by almost nobody. A wage bill that is far too small points to workers who were on site without being declared.
Who needs it
The check applies to all public works. It also applies to private works with a value of €70,000 or more.
Il DURC di congruità belongs to one specific work, not to a company. Each project is assessed on its own figures. Workers posted to the site by an employer based abroad count towards the declared labour like everyone else.
Where to get it
Il committente (the client) or l'impresa affidataria (the main contractor on site) requests the certificate. This happens at the last progress statement on the works, before the final payment. La Cassa Edile (the welfare fund for the construction sector) issues it.
The calculation runs through la CNCE, the national body of the construction welfare funds, and its Edilconnect system. It uses the reference percentages set for il CCNL edilizia, the national collective agreement for construction. Those tables show, for each type of work, how much of the total value labour is expected to represent. The system and the reference tables are kept by the CNCE.
What to watch out for
A shortfall of up to 5 percent can be justified by il direttore dei lavori (the works director). Above that, the main contractor has 15 days to pay the difference in contributions. In practice, the final payment is held back until the difference is paid.
Il DURC (the ordinary certificate of social-security compliance) describes a company. Il DURC di congruità describes one work. Neither replaces the other. A company can be fully in order on its ordinary DURC and still answer for a project whose declared labour does not add up.
Il DURC di congruità is not a certificate for one subcontract. It covers the works as a whole, and its outcome concerns the main contractor.